New Schedule Lag and Lead Options

Dave Robertson
January 21, 2021
5 min read

Now you can build Lag and Lead Times into your project schedule dependencies for tasks that need a delay or a head start.

Lag ('delayed starts')

Lag can be used to build in 'delays' into your project schedule.

Lag Time Examples:

For example, let's say you get your countertops measured and it's going to take 10 days for the counters to be fabricated, delivered and installed.  You could build in a 10 day 'lag' into the dependency between measurement & installation to show that delay.

Lag File

Leads ('head starts')

You can also build in a 'head-start' to your dependencies if you want a task to start earlier.

Lead Example

For example, in your schedule you may have Exterior Painting starting after the Windows have been installed, but let's say you want your Painters to come out 1 day early to start the prep work (taping off windows, caulking trim, etc.).

Lead GIF


Dave Robertson
January 21, 2021
5 min read
Our blog

Other Recent Blog Posts

New Features

Stay in the Loop with Project Updates in Your Daily & Weekly Digests!

FlipperForce's Daily and Weekly Digest emails now feature a "Project Updates" section, providing a snapshot of recent project activity.
November 14, 2024
5 min read
New Features

Flip Analyzer & BRRRR Analyzer now supports 3 decimals on Financing Calculations

Perform more accurate financing calculations with 3 decimal places for interest rates & points.
Dave Robertson
October 31, 2024
5 min read
New Features

Workspace Tasks: Centralized Task Management Across Projects

Our new Workspace Tasks feature brings all your project tasks into one central hub, eliminating the need to jump between projects.
Dave Robertson
October 17, 2024
5 min read
New Features

Improved Daily and Weekly Digest Emails!

We've made significant improvements to the Daily and Weekly Digest emails to provide the clarity and organization you need to stay on top of your Tasks, Schedules, and Events.
Dave Robertson
September 19, 2024
5 min read
New Features

Customize your Pipeline Workflow Stages!

Tailor your Pipeline workflows and Stage names to match your exact business process.
Dave Robertson
September 4, 2024
5 min read
New Features

Calendar View Modals Get a Makeover!

Schedule and Task modals in the Calendar view now feature a "Project Header" to clearly indicate the associated project, enhancing clarity when managing multiple projects.
Dave Robertson
August 16, 2024
5 min read

Ready to Take Action?

Sign up for a free trial and join over 1,000 house flippers and real estate investors that have taken their business to the next level!