How do I create a connection between tasks on the Scheduler?

How do I create a connection between tasks on the Scheduler?

To connect/link Tasks on the Project Scheduler, place your pointer at the front/end of the Task, hold down the pointer and drag the connector to the end of the Predecessor Task.

To connect/link Tasks on the Project Scheduler, place your pointer at the front/end of the Task, hold down the pointer and drag the connector to the end of the Predecessor Task.