What is the % Complete Column on the Project Budgeter?

The % Complete Column is the estimated amount you have completed for a Category.  The % Complete is used to calculate the Projected Final Costs for that Category, which is ultimately compared to your Budgeted Amount.

Projected Formula‍

  • Projected = Spent to Date / % Complete
  • Variance = Projected - Budgeted

Example

Ex: Let's say you had an initial budget of $4,000 for roofing.   There was a change order and the roofing ended up costing $4,500.

  • Projected = $4,500 / 100%= $4,500
  • Variance = $4,500 - $4,000= +$500 over budget