What is the % Complete Column on the Project Budgeter?

Disclaimer: FlipperForce does not provide tax, legal, or accounting advice. This report and FAQ are for informational purposes only and should not be soley relied upon for tax compliance. Because IRS rules are complex and subject to change, we strongly recommend consulting with a qualified tax professional or accountant before making business decisions or filing returns.

The % Complete Column is the estimated amount you have completed for a Category.  The % Complete is used to calculate the Projected Final Costs for that Category, which is ultimately compared to your Budgeted Amount.

Projected Formula‍

  • Projected = Spent to Date / % Complete
  • Variance = Projected - Budgeted

Example

Ex: Let's say you had an initial budget of $4,000 for roofing.   There was a change order and the roofing ended up costing $4,500.

  • Projected = $4,500 / 100%= $4,500
  • Variance = $4,500 - $4,000= +$500 over budget

Related Video

Project Budgeter Overview - Managing Your Rehab Budget
Learn how to use the Project Budgeter to Manage Your Rehab Budget, Track Your Project Expenses and Forecast Project Profitability.
4:19
Avatar photoAvatar photoAvatar photo

Still Have Questions?

Can’t find the answer you’re looking for? Please chat to our friendly team.